Casting production control

Plan the shift around the limiting stage.

Translate pouring, moulding and finishing capacity into a realistic casting production plan for a single product and shift.

At a glance
  1. MouldingMoulds ready to pour
  2. PouringHeat and grade capacity
  3. FinishingFettling and inspection capacity

Make bottlenecks visible before releasing work

Put all capacities on a common basis

For a single part, translate mould availability, compatible metal and finishing capacity into pieces per shift. Account for cavities per mould and the part’s actual poured weight, including its share of runner and riser metal when converting melt capacity.

Keep the constraint specific

A moulding line can have capacity in total while the pattern you need is unavailable. A furnace can have capacity for the shift while a grade change makes it impractical for the selected orders. Separate capacity by part family and grade before relying on an aggregate number.

Carry WIP across shifts explicitly

Record the count already waiting for finishing, and reserve inspection and dispatch capacity for due orders. Track whether the bottleneck moved during the shift. Review held batches and their next planned release alongside the pieces completed.

Shift bottleneck estimator

Enter effective capacities in pieces per shift for one part. This estimate assumes a steady flow with no opening buffer between stages.

Formula · lowest stage capacity sets the estimated throughput

Explore Envisage ERP

Envisage ERP covers mould-line and metal capacity planning, stage-wise WIP and foundry job logs. Ask how the planning view exposes the constraint for one grade and one part family.